BCHOD undertook Geotechnical investigations and report plus the rehabilitation of the the Cam and Motor TSF. The summary of works undertaken in the rehabilitation of the Cam and Motor TSF are as follows;
- Access road construction
- Tailings/slimes push back
- Buttressing wall construction
- Toe drain construction
- Return and storm water ponds construction
- Floating penstock and pipework construction
- Top of dam and penstock access catwalk construction
- Tailings disposal lines construction
- Return water pipelines (HDPE) installation
- Piezometers Installation
- 11.monitoring boreholes installation
- Perimeter fencing